2008-09-29
Duck House ~ "How To Tips, Part VI"
Today, the rafters were put in and secured. I am happy to report that all of the little birdies kept their mouth shut and they fit snugly into place. Bird blocks are also installed and secured. In case I am to busy to blog tomorrow, I expect to install the nailers and finish the siding at the front and rear peaks. Cut out one of my form fitting rafters and frame in the sky light, install the soffits as well as the gable end at the rear of the building. Perhaps, if time permits start laying the plywood on the roof.
For some reason, I think the birds believe that I am building them a new home. After I finished the cofferdam on the pit, a Magpie stopped by to visit while I was sitting in a nearby chair. He walk all around the perimeter of the cofferdam, peering down into pit. Today, while sitting in the same chair and continuing my contemplation, a Canadian Jay stopped by and had to inspect the the ridge beam by strutting back and forth. The first sea gull visited the HITW by landing in the middle of the parking lot, but that is a different story which I will not go into. While on the subject of birds, although I have not actually witnessed their presence. They seem to like the color of the trim on the Wolf Den. The ridge beam that extends beyond the roof line must make a nice perch, the "Blueberry" color is now highlighted with patches of white. I assume, they could not wait for the "Duck House" to be completed. This morning each of the roof tops on the cabins were white with frost, would have been neat to see a little smoke curling up from a chimney, but I guess we had better install a stove first.
2008-09-27
Duck House "How To Tips" ~ Part V
Finished up the siding today and installed the roof beams. The structure continues to remain true to square, well at least within a 1/4 inch tolerance. The main lesson I learned the last two days, "do not reflect on what you have done or currently doing but concentrate on the next step".
I got the two windows framed in, so we should have plenty of light. The larger window will be on the south side with a smaller window to the right of the door. In our "old" Duck House" it was always difficult to tell if the facility was in use, so I thought a front window would eliminate this problem.
Finished up the siding this morning and a very good lesson was learned in this process. When laying on siding, one should cut out the door opening prior to installing the last of sheet of siding. Although, I could have possibly found the door opening from the outside, however, I chose to insure that I did not cut the door where it should not have been cut. With the assistance of a ladder, I was able to access the top of the frame, raise the ladder and lower it into the inside of the building to access the floor. It was then simple to cut out the door and plate between the door frame.
I must admit, it did take a period of time and several practice cuts to determine the right angle for the roof support beams on the deck. Once again, I put my "palm nailer" to good use when "spiking" the timbers to the base and overhang. Although, most will laugh at my "crude skills" but when pricing lumber, I discover that 4" X 4" dimensional lumber is very expensive and perhaps over kill on a project this size. In place, I chose to use two 2" x 4"s and made a laminated beam. Using one quart of Gorilla Glue, I laminated the two beams and then insured the security by driving forty three nails on each side of the beam. They may fall down, they may break but they will never come apart. I love Gorilla Glue!
So far all things have went well, no bodily injuries but have been having equipment problems. Yesterday, I had to take time off to re-install the pull cord on the generator. Some how it fell off. Today, went to plug in the grinder to sand off a little excess Gorilla Glue that was seeping from the sides of the glue lam. Went to straighten one of the prongs on the plug to plug it in and it broke off. A quick trip to the hardware store for a new plug and 15 minutes to install. The biggest problem was that someone left the damm air hose to the nail gun laying in the same area that I was cutting framing materials, a rubber hose is no match for a circular saw, however, the excessive noise of rushing air will definitely get your attention. Now I know why contractors like to bid a job on "material and time". But, I am having fun!
2008-09-22
Duck House ~ "How To Tips Part IV"
Finished up the framing today, the four walls are now standing and squared. I can fully appreciate that it is much easier to place the siding on the walls and then stand them, however, working with a "short crew", it is really not an option especially when you have to build them "off site" and carry them to the construction site. Squaring things up required a little ingenuity, I know some prefer to use a "coffin jack", an option that I had available to me, however, I chose the "Old Navy" (1960'era) method of putting a strain on an object called a "Mexican Windless". All you need is one piece of line, doubled up and a object to twist it to the desired tension. In this situation, I used a nylon line and a stub end of a 2" x 4" as the windless (pictured across the front of the framing). It worked perfectly and the alders that I was using as an anchor remained rooted. If it is not raining come first light, the next step will be to side the frame and move on to the cutting and installing the rafters. If a certain person who was the Foreman on the the "Cabin II Project" is wondering, yes! I got the California corners installed on the right side and even remembered to nail them completely instead of free floating them. Having fun, putting a few "tricks of the trade" that I learned this summer to use and discovering others.
2008-09-19
Duck House ~ "How To Tips, Part III
My Apprentice Is Not Much Help, But He Keeps An Eye On What Is Going On. The Hole In The Ground Arouses His Curiosity. Site Had It's Final Grading And The Foundation Laid. Perhaps, With Another Good Day Of Weather, The Decking Will Be Laid And Some Walls Standing.
To add to your "How To" notes, foundation is formed from green, treated all weather wood, 2"x 6" in dimension on 16" centers. Leveled and tied into the rim of the pit cofferdam. When building, insure you check on a regular basis to insure that the foundation remains square as well as level. It is fully appreciated that the "green wood" is laced with known contaminants, however, knowing that the water table is at least eight feet below the surface, a little leeching of arsenic should have no immediate harmful effects.
2008-09-17
HITW "STRIKE"
Brought the "Little Mole" in today to assist in the re-excavation of depository site. It was only after I lowered her into the hole and removed the ladder, that I realized that this was the second septic system that she has dug this season. She was a trooper, no breaks even when I called for one, the five minute breaks were reduced to two minutes. Due to the depth of the pit and her vertical handicap (5'1") the dirt had to be transferred out of the site by the use of two five gallon buckets and pulling lines. The first lesson learned, DO NOT FILL A FIVE GALLON BUCKET FULL OF SAND AND GRAVEL. The pulling engine did not have enough horsepower so the transfer was reduced to half buckets. The first hundred or so buckets were used to back fill the cofferdam with the remainder being leveled off surrounding the pit foundation. We exceeded the original depth, to an actual pit depth of 7 feet 10 inches. From original ground level, it is approximately nine feet deep. Although a few "unique" rocks were discovered showing some color, no gold in nugget form was discovered. However, we did go deep enough to STRIKE water. At this point, we called off further dredging to keep from entering the aqua firm, however, it may be something to keep in mind. The water level is likely to be in the nine to ten foot range in the area of the HITW. Useful information in the event a water system is considered in the future.
"My Mole"
Following the dredging, the site was leveled with a very good quality of sand and gravel from the dredging operation in preparation for laying the foundation of the building. Should provide some excellent drainage and excellent building platform. It is hope, that weather permitting the foundation and decking will be taken care of tomorrow. In the event of rain, perhaps a trip to the big lumber yard to pick up a supply a dimensional framing lumber and siding. I am here to tell you, all of you are missing out on a lot of fun!
2008-09-16
Great Flood of "September 08"
Moose Park and Emergency Evacuation Boat
Granny's Gully Creek
John's Glacier Creek
"Ruger" Eyeballing Situation
2008-09-15
Duck House "How To Tips, Part II"
2008-09-11
"Duck House" How To Tips Part 1
First thing you will want to do is select a site that not only is soothing to the soul in natural fauna and floral, but also has a good base for drainage. We were fortunate to select such a site. Early into the excavation, a very good quality of sand and gravel was struck enabling the excavation to go to a depth of seven feet and provide instant draining of liquids.
The first error occurred by not covering the site and allowing rain to saturate the area, eroding about three feet of top soil into the excavation site.
Today, construction began in earnest with the removal of the original foundation base and excavating around the perimeter of the excavation.
Referring back to my engineering notes as well as the building plans, the site was further excavated to including the entire perimeter of the building and deck structure, to insure the ground was level, well drained for building construction.
Although a lot of material had to be moved by hand in the excavation process, the site came out level and should drain well. Additional back filling around the pit entrance will take place at a later stage in the project. Water repellent material was then added to the substructure above and below ground level.
Additional fabric was placed on the substructure to insure that water was diverted from the site, allowing it to saturate into the sand, gravel, and not drain directly into the excavation creating a second erosion problem. Additional back fill will be placed around the substructure to bring the foundation of the building level with the top of the substructure.
It was a beautiful day to work at the HITW today, some sunshine and shirt sleeve weather. Weather permitting, tomorrow, the soil abatement cofferdams will be built for installation inside the substructure, the messican excavator will be on the job site to extricate the excess debris from the bottom of the depository. Although primitive, I believe that with one on the digger and the second on the five gallon bucket, it should be a simple task to take it back to the original depth or perhaps a little deeper. Once completed, the foundation for the building can be completed before another trip to the lumber yard is required. I did spend a little time in the bottom of the pit today, only to extricate my engineering calculator that had slipped out of my shirt pocket as well as the level that accidentally drop into the hole during the process of leveling.
In the event you are wondering, I am having fun! As a side note, now I do not want to start a major "rush" to stake claims, but perhaps I have discovered "Arnie's Vein". I excavated a rock today, about half the size of a football. I was totally amazed by the amount of "gold" that is showing in the rock, perhaps the most I have ever seen show in one rock. It is safely stowed away in my safe, however, next spring it will be on public display in the new "Duck House", under very tight security. Having plenty of time to think today while shoveling, you can look forward to some innovative improvements to Duck House II.
2008-09-09
Rain and Dirt Problems
2008-09-03
Final Test Completed
2008-09-01
Labor Day
All of the goals that I had hoped to see achieved was accomplished ahead of schedule and we are in great shape. Cabins are all dried in, windows, doors, and mostly painted except from trim work. First cabin is 90% completed and second cabin 80% completed. Possibly the best depository that I have ever seen dug was completed to a depth of 7 feet in a high quality of sand and small gravel. Two hundred feet of water line dug in and laid, could have running water in the time it takes to have it delivered to the tank. Both cabins on shore power and engineered for underground lines. Excess building material located to one spot and covered for winter, waiting for spring to be uncovered and start all over again on the 2nd phase.
Overall, it was a great weekend and from both of us, to all of you; Thank you for your efforts and the amount of time and labor you have contributed. We are now two steps closer to achieving the dream that was conceived several years ago. Job well done to all Clans, family and good friends.